The City of Coppell
File #: 2023-7232    Version: 1 Name: Library Internal Gutter Replacement
Type: Agenda Item Status: Passed
File created: 12/1/2023 In control: Engineering
On agenda: 12/12/2023 Final action:
Title: Consider approval of awarding a contract to Next Gen Construction, LLC (TIPS #23010402); for the replacement of the internal Gutter System at the Cozby Library and Community Commons; in the amount of $140,000.00; as budgeted in Infrastructure Maintenance Fund; and authorizing the City Manager to sign any necessary documents.
Attachments: 1. Memo.pdf, 2. Quote.pdf

Title

Consider approval of awarding a contract to Next Gen Construction, LLC (TIPS #23010402); for the replacement of the internal Gutter System at the Cozby Library and Community Commons; in the amount of $140,000.00; as budgeted in Infrastructure Maintenance Fund; and authorizing the City Manager to sign any necessary documents.

Summary

 

Fiscal Impact:

The fiscal impact of this agenda item is $140,000.00, as budgeted in the Infrastructure Maintenance Fund.

 

Staff Recommendation:

The Public Works Department recommends approval.

 

Strategic Pillar Icon:

 

Sustainable Government