Title: Consider award for approval of a design contract change order with Parkhill; for the final architectural design of the City of Coppell Service Center Improvements; in the amount of $590,949.18; funded from undesignated fund balance of the General Fund, then reimbursed in accordance with the Reimbursement Resolution approved on April 12, 2022; and authorizing the City Manager to sign any necessary documents.
Attachments: 1. Memo.pdf, 2. Agreement.pdf

Title

Consider award for approval of a design contract change order with Parkhill; for the final architectural design of the City of Coppell Service Center Improvements; in the amount of $590,949.18; funded from undesignated fund balance of the General Fund, then reimbursed in accordance with the Reimbursement Resolution approved on April 12, 2022; and authorizing the City Manager to sign any necessary documents.

Summary

 

Fiscal Impact:

The fiscal impact of this agenda item is $590,949.18 funded from assigned fund balance of the General Fund, then reimbursed in accordance with the Reimbursement Resolution approved on April 12, 2022.

 

Staff Recommendation:

The Public Works Department recommends approval.

 