The City of Coppell
File #: 2023-7233    Version: 1 Name: SC Design Change Order
Type: Agenda Item Status: Passed
File created: 12/1/2023 In control: Public Works
On agenda: 12/12/2023 Final action:
Title: Consider award for approval of a design contract change order with Parkhill; for the final architectural design of the City of Coppell Service Center Improvements; in the amount of $590,949.18; funded from undesignated fund balance of the General Fund, then reimbursed in accordance with the Reimbursement Resolution approved on April 12, 2022; and authorizing the City Manager to sign any necessary documents.
Attachments: 1. Memo.pdf, 2. Agreement.pdf

Title

Consider award for approval of a design contract change order with Parkhill; for the final architectural design of the City of Coppell Service Center Improvements; in the amount of $590,949.18; funded from undesignated fund balance of the General Fund, then reimbursed in accordance with the Reimbursement Resolution approved on April 12, 2022; and authorizing the City Manager to sign any necessary documents.

Summary

 

Fiscal Impact:

The fiscal impact of this agenda item is $590,949.18 funded from assigned fund balance of the General Fund, then reimbursed in accordance with the Reimbursement Resolution approved on April 12, 2022.

 

Staff Recommendation:

The Public Works Department recommends approval.

 

Strategic Pillar Icon:

 

Sustainable Government