File #: 2020-5383    Version: 1 Name: Annual Street/Alley Renewal
Type: Agenda Item Status: Passed
File created: 11/2/2020 In control: Public Works
On agenda: 11/10/2020 Final action:
Title: Consider approval of award for the contract to two separate contractors; each performing a share of the ADA sidewalk repairs and annual street and alley pavement repair program; in the amounts of $540,000.00 to F&F Construction and $360,000.00 to New World Contracting; for a total of $900,000.00; as budgeted in the Infrastructure Maintenance Fund; and authorizing the City Manager to sign any necessary documents.
Attachments: 1. Annual Street and Alley Memo.pdf, 2. Annual Street, Alley and Sidewalk Bid Tab.pdf, 3. Contract Award Split Calculations.pdf, 4. New World Bidder Review Letter.pdf

Title

Consider approval of award for the contract to two separate contractors; each performing a share of the ADA sidewalk repairs and annual street and alley pavement repair program; in the amounts of $540,000.00 to F&F Construction and $360,000.00 to New World Contracting; for a total of $900,000.00; as budgeted in the Infrastructure Maintenance Fund; and authorizing the City Manager to sign any necessary documents.

 

Summary

 

Fiscal Impact:

The fiscal impact of this agenda item is $900,000 as budgeted in the Infrastructure Maintenance Fund.

 

Staff Recommendation:

The Public Works Department recommends approval.

 

Strategic Pillar Icon:

 

Sustainable Government